Project Description
MEC successfully commissioned the Rural Electrification Extension Project, Phase-II (REEP-II) for National Water and Electricity Company ltd (NAWEC) involving design, supply, installation, testing & commissioning of the following: –
- 128 Km of 30 KV medium voltage transmission lines
- 2.38 MWp power plant at Farafenni & 2.68 MWp power plant at Bassi
- Associated low voltage distribution network
Client
National Water and Electricity Company ltd
End Date
30th Oct 2018
Type of Contract
Turnkey Transmission-Distribution-Power Generation project