Project Description

The project involved laying of 150 km of 225 KV transmission line between Republic of Mali and Republic of Cote d’lvoire.

Client

Ministry of Energy and Water

End Date

12th Oct 2014

Type of Contract

Turnkey Transmission Line Project

Challenges

  • Pneumatic hammers used for rock blasting 1 meter underneath the soil
  • Special Towers were designed and installed to cater to long spans
  • Superior Piling technology was used